Weather permitting, the follow lane closures are scheduled:
I-95 North night work
When: Aug. 31 to Sept. 1, 9:30 p.m. to 5 a.m.
What: Two lanes closed
Where: I-95 north, from the U.S. 1 on ramp to Exit 163, Lorton Road (Va. 642)
Why: Shifting traffic lanes
Police: Onsite for motorist safety
I-95 South night work
When: Sept. 2 and 3, 9:30 p.m. to 5 a.m.
What: Two lanes closed
Where: I-95 south, from the Pohick Creek Bridge to Exit 161, U.S. 1
Why: Shifting traffic lanes
Police: Onsite for motorist safety
I-95 North day work
When: Aug. 31 to Sept. 3, 9:30 a.m. to 3:30 p.m., and Sept. 4, 9 a.m. to noon
What: Right lane closed
Where: I-95 north, from the U.S. 1 on ramp to one mile south of Exit 166, Fairfax County Parkway (Va. 7100)
Why: Grading, sound wall and bridge work
I-95 South day work
When: Aug. 31 to Sept. 3, 8 a.m. to 2 p.m.
What: Right lane closed
Where: I-95 south, from Exit 166, Fairfax County Parkway (Va. 7100) to Exit 160, Gordon Boule-vard (Va. 123)
Why: Bridge work
Furnace Road (Va. 611) east OR west day work
When: Aug. 31 to Sept. 3, 9:30 a.m. to 3:30 p.m.
What: Single lane closed (Flaggers to direct alternating traffic)
Where: Furnace Road (Va. 611) east OR west, at I-95 south
Why: Placing steel girders and installing diaphragms
VDOT is adding a fourth general purpose lane to I-95 in each direction from U.S. 123 just before the Occoquan River to the Fairfax County Parkway. The agency says this will relieve chronic bottlenecking and improve traffic flow to and from the Springfield Interchange. Construction of the six-mile widening project began in early 2008 and will be completed by late fall 2011.