I-95 North night work
When: Sept. 14 to17, 9:30 p.m. to 5 a.m.
What: Two right lanes OR two left lanes closed (at least one lane open to through traffic at all times)
Where: I-95 north from Exit 160, Gordon Boulevard (Va. 123), to Exit 163, Lorton Road (Va. 642)
Why: Mill and asphalt pavement
Police: Onsite for motorist safety
I-95 North day work
When: Sept. 14-17, 9:30 a.m. to 3:30 p.m., and Sept. 18, 9 a.m. to noon
What: Right lane closed
Where: I-95 north from the Route 1 on ramp to just before Exit 166, Fairfax County Parkway (Va. 7100)
Why: Grading, MSE wall, combo wall and bridge work
I-95 South day work
When: Sept. 14-17, 8 a.m. to 2 p.m.
What: Right lane closed
Where: I-95 south from Exit 166, Fairfax County Parkway (Va. 7100) to Exit 160, Gordon Boulevard (Va. 123)
I-95 HOV Day Work
When: Sept. 14 to 17, 9:30 a.m. to 3:30 p.m., and Sept. 18, 9 a.m. to noon
What: Single lane closed
Where: I-95 HOV from Lorton Road (Route 642) to Gordon Boulevard (Route 123)
Why: Setting barriers to work on light blisters and overhead signs
Lorton Road (Route 642) East and West Day Work
When: Mon. through Thu., Sept. 14-17, 9:30 a.m. to 3:30 p.m., and Fri., Sept. 18, 9 a.m. to noon
What: Single alternating lane closed
Where: Lorton Road (Route 642) east and west between Gunston Cove and Silverbrook roads
Why: Working on median barrier
Furnace Road (Route 611) East OR West Day Work
When: Mon. through Thu., Sept. 14-17, 9:30 a.m. to 3:30 p.m.
What: Single lane closed (Flaggers to direct alternating traffic)
Where: Furnace Road (Route 611) east OR west at I-95 south
Why: Installing diaphragms and demolition of existing bridge
VDOT is adding a fourth general-purpose lane to I-95 in each direction from Route 123 just before the Occoquan River to the Fairfax County Parkway. The agency said this will relieve chronic bottlenecking and improve traffic flow to and from the Springfield Interchange. Construction of the six-mile widening project began in early 2008 and will be completed by late fall 2011.